        <journal-title>《建筑施工与发展》</journal-title>
        <abbrev-journal-title>CONSTRUCTION AND DEVEL OPMENT</abbrev-journal-title>
      </journal-title-group>
      <issn>ISSN：2737-4262；EISSN:2705-1269</issn>
      <publisher>
        <publisher-name>华文科学出版社</publisher-name>
      </publisher>
    </journal-meta>
    <article-meta>
      <article-id pub-id-type="doi">10.12361/2705-1269-7204-132</article-id>
      <article-id pub-id-type="publisher-id">12130</article-id>
      <title-group>
        <article-title>大跨度屋面钢桁架滑移施工模拟分析</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <string-name>王冠男 张 旭 高少磊 中信建设有限责任公司 北京 100027</string-name>
        </contrib>
      </contrib-group>
      <pub-date pub-type="epub">
        <year>2025</year>
        <month>3</month>
      </pub-date>
      <issue>3</issue>
      <abstract>
        <p>某大跨度屋面大跨度屋面钢桁架结构尺寸为 60m*108m，由于场地的限制，采用累积滑移的施工方案，需要在端部搭设高空拼装
胎架，块体拼装直接在高空胎架完成。本文采用 SAP2000 建立有限元分析模型，对大跨度屋面钢桁架结构的施工方案和施工过程有限元仿
真，对比不同的滑移单元的划分方案。对最终的施工方案进行有限元仿真分析，对其施工过程中的变形和应力进行分析。计算结果表明，
施工模拟过程中最大位移发生在桁架的跨中位置，其中结构整体的位移呈先增大后减小的趋势，最终最大的 Z 向变形为-52.88mm，满足
1/1000 的变形要求。考虑施工模拟和正常使用极限状态的应力比计算，构件最大应力比为 0.83，满足设计要求。
关键词：大跨度屋面大跨度屋面钢桁架结构，施工模拟分析</p>