<?xml version="1.0" encoding="UTF-8"?>
<!DOCTYPE article PUBLIC "-//NLM//DTD JATS (Z39.96) Article Authoring DTD v1.4 20240229//EN" "JATS-articleauthoring1.dtd">
<article article-type="research-article" xml:lang="zh-CN" xmlns:xlink="http://www.w3.org/1999/xlink">
  <front>
    <journal-meta>
      <journal-id journal-id-type="publisher-id">29</journal-id>
      <journal-title-group>
        <journal-title>《建筑施工与发展》</journal-title>
        <abbrev-journal-title>CONSTRUCTION AND DEVEL OPMENT</abbrev-journal-title>
      </journal-title-group>
      <issn>ISSN：2737-4262；EISSN:2705-1269</issn>
      <publisher>
        <publisher-name>华文科学出版社</publisher-name>
      </publisher>
    </journal-meta>
    <article-meta>
      <article-id pub-id-type="doi">10.12361/2705-1269-7311-121</article-id>
      <article-id pub-id-type="publisher-id">17636</article-id>
      <title-group>
        <article-title>大跨度钢桁架施工技术与管理实践</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <string-name>刘 刚 高海峰 曹雪峰 张祥飞 辛露露 中国建筑一局（集团）有限公司西北分公司</string-name>
        </contrib>
      </contrib-group>
      <pub-date pub-type="epub">
        <year>2025</year>
        <month>11</month>
      </pub-date>
      <issue>11</issue>
      <abstract>
        <p>在建筑工业化快速发展的背景下，大型钢结构厂房项目呈现出跨度大、工期紧、多专业交叉复杂的特点。本文以汉中市 930 号翼
身对接厂房项目为实践载体，针对超大跨度钢桁架施工中面临的场地限制、高空作业风险、多专业协同等管理难题，构建了"三维立体管理
模型"，即方案决策模型、资源动态调配模型、风险量化管控模型。通过管理流程再造、BIM 协同平台应用、工序模块化分解等创新手段，
实现了跨部门高效协作，成功将 75m 跨度桁架安装工期压缩 35%。本文从技术实施与管理创新相结合的角度，详细阐述了管理工具创新、
组织模式变革、决策机制优化等核心内容，为同类工程提供了可复制的技术与管理经验参考。
关键词：钢桁架；超大跨度；三维立体管理模型；跨部门协作</p>