<?xml version="1.0" encoding="UTF-8"?>
<!DOCTYPE article PUBLIC "-//NLM//DTD JATS (Z39.96) Article Authoring DTD v1.4 20240229//EN" "JATS-articleauthoring1.dtd">
<article article-type="research-article" xml:lang="zh-CN" xmlns:xlink="http://www.w3.org/1999/xlink">
  <front>
    <journal-meta>
      <journal-id journal-id-type="publisher-id">29</journal-id>
      <journal-title-group>
        <journal-title>《建筑施工与发展》</journal-title>
        <abbrev-journal-title>CONSTRUCTION AND DEVEL OPMENT</abbrev-journal-title>
      </journal-title-group>
      <issn>ISSN：2737-4262；EISSN:2705-1269</issn>
      <publisher>
        <publisher-name>华文科学出版社</publisher-name>
      </publisher>
    </journal-meta>
    <article-meta>
      <article-id pub-id-type="doi">10.12421/JZSGYFZ2705-1269-25071573</article-id>
      <article-id pub-id-type="publisher-id">20978</article-id>
      <title-group>
        <article-title>BIM+无人机技术在复杂幕墙工程进度管理中的协同应用研究</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <string-name>成俊凯 广州珠江监理咨询集团有限公司</string-name>
        </contrib>
      </contrib-group>
      <pub-date pub-type="epub">
        <year>2025</year>
        <month>15</month>
      </pub-date>
      <issue>15</issue>
      <abstract>
        <p>复杂幕墙工程因造型异形化、构件模块化、施工高空化等特点，传统进度管理方法易出现信息滞后、数据失真、协同低效等问题，
导致进度偏差风险升高。为实现复杂幕墙工程进度的精准化、动态化管理，本文提出“BIM + 无人机”协同应用技术框架。首先通过文献
梳理与工程调研，分析复杂幕墙工程进度管理的核心难点；其次构建 BIM 与无人机技术的协同机制，明确无人机航拍数据采集、BIM 模
型进度关联、数据融合分析三大关键环节；最后以广州某超高层综合体复杂幕墙工程为实例，验证该协同应用方案的可行性与实用性。结
果表明，该技术框架能实现幕墙施工进度的实时可视化监控，进度偏差识别效率提升 60% 以上，进度调整响应时间缩短 50%，有效保障
了复杂幕墙工程按计划推进，为类似工程的进度管理提供了技术参考。
关键词：BIM 技术；无人机技术；复杂幕墙工程；进度管理；协同应用</p>