<?xml version="1.0" encoding="UTF-8"?>
<!DOCTYPE article PUBLIC "-//NLM//DTD JATS (Z39.96) Article Authoring DTD v1.4 20240229//EN" "JATS-articleauthoring1.dtd">
<article article-type="research-article" xml:lang="zh-CN" xmlns:xlink="http://www.w3.org/1999/xlink">
  <front>
    <journal-meta>
      <journal-id journal-id-type="publisher-id">29</journal-id>
      <journal-title-group>
        <journal-title>《建筑施工与发展》</journal-title>
        <abbrev-journal-title>CONSTRUCTION AND DEVEL OPMENT</abbrev-journal-title>
      </journal-title-group>
      <issn>ISSN：2737-4262；EISSN:2705-1269</issn>
      <publisher>
        <publisher-name>华文科学出版社</publisher-name>
      </publisher>
    </journal-meta>
    <article-meta>
      <article-id pub-id-type="doi">10.12421/JZSGYFZ2705-1269-25071673</article-id>
      <article-id pub-id-type="publisher-id">21863</article-id>
      <title-group>
        <article-title>狭小场地条件下660MW机组直流塔式锅炉钢架吊装技术创新与应用</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <string-name>赵小林 李作鹏 中国能源建设集团天津电力建设有限公司</string-name>
        </contrib>
      </contrib-group>
      <pub-date pub-type="epub">
        <year>2025</year>
        <month>16</month>
      </pub-date>
      <issue>16</issue>
      <abstract>
        <p>针对火力发电机组向大容量、高参数发展中面临的施工场地狭小、吊装作业空间受限等技术难题，以国投钦州电厂三期 4×660MW
机组工程为研究对象，创新提出"分段吊装+机械混合使用"技术方案。通过系统优化机械选型与布置、采用模块化施工工艺、精确计算吊装
负荷、结合 BIM 技术模拟验证等综合措施，有效解决了复杂工况下的锅炉钢架吊装难题。工程实践表明，该技术方案将吊装工期从 120 天
缩短至 98 天，节约成本约 130 万元，安装精度误差控制在 3mm 以内，实现了安全、优质、高效的施工目标，为同类工程提供了重要参考。
关键词：直流塔式锅炉；钢架吊装；平臂吊；模块化施工；狭小场地；BIM 技术</p>