<?xml version="1.0" encoding="UTF-8"?>
<!DOCTYPE article PUBLIC "-//NLM//DTD JATS (Z39.96) Article Authoring DTD v1.4 20240229//EN" "JATS-articleauthoring1.dtd">
<article article-type="research-article" xml:lang="zh-CN" xmlns:xlink="http://www.w3.org/1999/xlink">
  <front>
    <journal-meta>
      <journal-id journal-id-type="publisher-id">29</journal-id>
      <journal-title-group>
        <journal-title>《建筑施工与发展》</journal-title>
        <abbrev-journal-title>CONSTRUCTION AND DEVEL OPMENT</abbrev-journal-title>
      </journal-title-group>
      <issn>ISSN：2737-4262；EISSN:2705-1269</issn>
      <publisher>
        <publisher-name>华文科学出版社</publisher-name>
      </publisher>
    </journal-meta>
    <article-meta>
      <article-id pub-id-type="doi">10.12421/JZSGYFZ2705-1269-080416-35</article-id>
      <article-id pub-id-type="publisher-id">30091</article-id>
      <title-group>
        <article-title>停工复建安置房 EPC 项目技术创效实践与研究</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <string-name>刘 刚 胡 伟 张祥飞 辛露露 蹇振强 中国建筑一局（集团）有限公司西北分公司 陕西西安 710000</string-name>
        </contrib>
      </contrib-group>
      <pub-date pub-type="epub">
        <year>2026</year>
        <month>7</month>
      </pub-date>
      <issue>7</issue>
      <abstract>
        <p>西安市长安区南雷村、北雷村、赤兰桥村城中村改造 EPC 总承包二标段属于回迁安置类工程，项目总建筑面积达 18.81 万平方米。
该项目曾长期停工，期间出现建设单位变更、现行技术规范更新以及交房标准调整等多重状况，复工后面临工期紧张、成本管控严格、分
包及劳务队伍稳定难度大、已完工程量确认复杂等现实难题。本文以该停工复建项目为研究对象，依托 EPC 模式下设计、采购、施工一体
化管理优势，围绕设计优化、施工方案迭代、施工工艺创新、既有资源再利用、正式工程替代临时设施五大核心方向，系统开展技术创效
策划与落地执行，构建覆盖外墙装饰、防水施工、室外管网、结构构件、机电安装及临时设施等全专业的技术创效体系，切实提高项目盈
利水平、工程实体质量与交付效率，可为同类停工复建安置房 EPC 项目开展技术创效工作提供可复制、可推广的实践经验与实施范式。
关键词：安置房建设；EPC 工程总承包；停工复建项目；技术创效；设计优化；成本管控；</p>