<?xml version="1.0" encoding="UTF-8"?>
<!DOCTYPE article PUBLIC "-//NLM//DTD JATS (Z39.96) Article Authoring DTD v1.4 20240229//EN" "JATS-articleauthoring1.dtd">
<article article-type="research-article" xml:lang="zh-CN" xmlns:xlink="http://www.w3.org/1999/xlink">
  <front>
    <journal-meta>
      <journal-id journal-id-type="publisher-id">8</journal-id>
      <journal-title-group>
        <journal-title>《科技研究》</journal-title>
      </journal-title-group>
      <issn>ISSN:3079-9244（原2717-5480）</issn>
      <publisher>
        <publisher-name>华文科学出版社</publisher-name>
      </publisher>
    </journal-meta>
    <article-meta>
      <article-id pub-id-type="doi">10.12421/ddyx3079-9244-2025302</article-id>
      <article-id pub-id-type="publisher-id">17040</article-id>
      <title-group>
        <article-title>北竹港护岸围堰工程优化探讨</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <string-name>徐海峰 （上海申鼎建设科技（集团）有限公司</string-name>
        </contrib>
        <contrib contrib-type="author">
          <string-name>上海宝山 200940）</string-name>
        </contrib>
      </contrib-group>
      <pub-date pub-type="epub">
        <year>2025</year>
        <month>3</month>
      </pub-date>
      <issue>3</issue>
      <abstract>
        <p>北竹港护岸围堰工程优化讨论，重点是顺河围堰改拦河围堰设计方案的调整。原设计方案利用顺河围堰进行设计，
因顺河围堰施工期面临水流阻力大，又因施工可能造成生态环境影响等原因，预计工期 12 个月，且施工难度较大，尤其在
恶劣天气条件下，施工进度难以保障，项目面临着较大的环境保护压力和施工安全风险。改拦河围堰，可有效降低水流对工
区扰动，增强施工可控性与安全性，优化施工进度。这个新的计划预期会将施工时间缩减到 8 个月，并使施工效率增加大约
33%。改进拦河围堰设计也能较好地维护周边水生生态、降低土方运输及环境污染、增强港口防洪能力。采用数值模拟和现
场监测数据相结合的方法，该研究对拦河围堰方案进行设计优化及实施效果进行论述，通过对施工期和施工期前后资料变化
情况进行比较和分析，为同类项目提供有价值的科学依据与技术支持。该优化方案在加强工程可行性的同时，也对后续同类
工程实施具有重要借鉴意义。</p>